Project JupiterMonday, Nov. 9, 2026 · Santa Teresa, N.M.
Project Jupiter: the progress report — a year in, the first building is topped out, and the project has no power
A year after the county approved $165B in bonds, the first building is topped out and 4,400 workers are on site. But the project has no power.
The air-permit hearing set for Dec. 7 is now in doubt. The gas pipeline was rejected twice. Oracle sent a notice that lets it delay rent up to 3 years.
The county that approved the bonds 4–1 just warned of a breach 5–0 over the El Paso Electric backup deal — then Oracle walked it back.
Water still has no full public accounting. The State Engineer says 1,445 acre-feet used so far. Oracle claims under a million gallons a year.
Compare that to El Paso: the state had no say in the Meta deal. City Council approved the Chapter 380 agreement in December 2023. In New Mexico, the state is everywhere in Jupiter — the State Engineer, the Supreme Court, the Attorney General, the Land Commissioner.
Voters just put longtime Jupiter opponent Daisy Maldonado on the county commission with 60%.
And in Texas, the new governor promised a moratorium on new data center approvals until the Legislature passes protections — Governor-elect Gina Hinojosa takes office January 19. Already-permitted projects, like Meta’s El Paso campus, finish as planned. The freeze is on what’s next, not what’s already rising.
Updated Nov. 10: the Dec. 7 hearing was vacated the next day — see the update below.
Project Jupiter · Air PermitTuesday, Nov. 10, 2026 · Santa Teresa
Dec. 7 air-permit hearing is off — vacated, no new date
The December 7 public hearing on Project Jupiter’s air permit is off — vacated November 6. No new date.
The developer and the state asked for it together. The developer revised its application in October, cutting projected emissions from 8.8M to 5.7M tons a year, and the state needs more time to review it. The developer also waived the November 23 deadline for the state to decide the permit, after saying on October 23 it would not.
The hearing was on air permit No. 10883 — the roughly 2.45 GW fuel-cell microgrid that would power the campus. The permit is still pending — not approved, not denied. Construction keeps going while the permit waits: the project was about 26% complete, with Building A topped out in October. The December hearing was the public’s day to speak on the record. That day is gone for now. Next date to watch: a November 19 status conference.
Sources: Las Cruces Sun-News, Nov. 6 · Organ Mountain News, Nov. 5